Case Studies & Testimonials

Whether a project is a single machine move or a factory relocation complete with CDM, they are all unique and all have a degree of risk. Find out what our customers say about our services… 

Case Studies

NEC Nightingale Hospital, Birmingham

AIS-Vanguard-NEC

“Neil and his team were instrumental to the build over at the NEC to deliver the Nightingale hospital and nothing was too much for them, helping in anyway they could.”

“From building the furniture and transferring it to the individual wards to helping at a moments notice getting bathroom pods in place using lift and shift equipment. The positive can do attitude that Neil, Jon and the lads had were second to none and even when we received the news that the beds were going to be late and I needed the lads to work a double shift, not only did they say yes but they absolutely smashed it.”

“I literally can’t tell you just how nice it was to work with such a great team that you have and although it may seem a little weird, it was a shame for the build to end, although very grateful that many more beds weren’t needed.”

Leigh Teaching Hospitals NHS Foundation Trust

“We would not have been able to successfully complete this project and open the ward on schedule, without AIS Vanguard’s extraordinary commitment and effort in assisting with the equipment transfer.”

“Bryn Ward will be a huge asset to the Wigan Borough in helping us care for those affected by the COVID-19 pandemic, ensuring we have the extra capacity we need to help our amazing and dedicated staff treat patients with COVID-19, safely and effectively;”

“Once again, we cannot emphasise enough the importance of this project being delivered on time and to achieve this is nothing short of remarkable.”

Technical Lift at the Stanley Lift Bridge in Tameside

After the recent success of a swing bridge lift in Skipton, West Yorkshire, Universal Coatings and Kier Construction again requested Ainscough Industrial to assist with a similar project.

Technical Lift at the Stanley Lift Bridge in Tameside

This project was to remove the Stanley Lift Bridge on the High Peak canal in Dukinfield, Tameside.

The 4 tonne bridge along with the lifting frames which had been in place for over 35 years were being removed for a full refurbishment and repaint.

Although this was a relatively small lift for Ainscough Industrial Services, there were still a number of challenges to overcome which included the confined space for the lift and the gas pipe which crossed the canal next to the bridge.

The first task was to remove the lifting frame from above the bridge which then allowed more space for the bridge to be lifted over the gas pipe and onto the waiting transport along with the frames.

The Ainscough team then assisted with the lifting and positioning of a temporary bridge over the canal, which was to be used by the local residents until the re-installation of the permanent bridge after its refurbishment approximately two weeks later.

Ainscough Industrial Assists With Concrete Kerb Packing Line Relocation

The client, Aggregate Industries quarries, manufactures and supplies a wide range of heavy building materials to the construction industry.

Packing-line-removal-by-Ainscough-Industrial

The three week project required the Ainscough team to completely match mark the packing line followed by the complete dismantling of all mechanical and electrical elements ready for the loading onto transportation to the new location.

On arrival at the new location the team then needed to offload the packing line and completely rebuild then align, and level and finally commission to ensure everything was running as it should.

Because of the complex nature of this relocation it was vital that every aspect of this project was meticulously planned to ensure a smooth transition to the complete satisfaction of the client.

Aggregate Industries Project Manager Mark Smedley kindly commented:

“The Ainscough team was a pleasure to work with on this project, with their professional attitude, methodical and diligent work practices everything was completed within the allocated time frame, and I look forward to working with the Ainscough team on any future projects that we have.”

If you would like any help or advice for your relocation project contact the Ainscough Industrial team today.

Turnkey Removal And Installation For A Paper Mill

AIS Vanguard, a division of Ainscough Industrial Services, were recently procured by Terex to provide a turnkey removal and installation of a 160 tonne Overhead Gantry Crane to Palm Paper, at a paper mill based in Kings Lynn in Norfolk.

AIS-Vanguard-Paper-Mill-Lift

The mill manufactures 450,000 tonnes of newsprint per year from recovered newspapers and magazines and supplies many of the UK’s regional and national newspaper publishers. It also produces a variety of other paper types for coldset, heatset and litho printing processes

Due to the access required, the first stage of the operation was to remove sections of the roof of the mill with the use of both tower and mobile cranes and support vehicles.

On completion of this two day procedure the Ainscough team was then able to decommission and lift the old gantry crane, which measured over 30 meters, out through the gap in the roof and on to transportation to be taken away.

The next part of the task was then to lift the new gantry crane in through the roof and lower to its final position ready for the installation process and commissioning.

Finally the sections of the roof were replaced. We were able to complete the entire project in less than five days, which was quicker than the programmed schedule.

Due to the size, weight and the unusual entry and exit for the gantry cranes it was vital that all aspects of this project including method statements and health and safety procedures were in order. We made sure that all of these documents were meticulously planned and adhered to throughout the project ensuring a smooth completion of the project.

This resulted in us finishing the lift project ahead of schedule, with minimal risk and to the complete satisfaction of the client.

On the completion of the project the client commented on how pleased they have been with the Ainscough team’s professionalism and working procedures.

If you would like more information about our turnkey machine removal and installation services contact the Ainscough team today.

Complicated Lift Completed By Ainscough Industrial

Ainscough Industrial was recently contracted by a well known cider maker to assist with a complex machinery lift and installation.

Fermentation-tank-installation-by-Ainscough-Industrial

Ainscough was brought in to assist with the positioning and installation of eighteen new fermentation vessels into their facility in Weston Super Mare.

The project consisted of three phases which will be completed over a five week period. Each phase involved the lifting and positioning of six of the fermentation vessels which were 14.5 meters high and had a weight of 8.5 tonnes into the facility over a two day period.

The first stage for the Ainscough team was to remove a 1.5 tonne section of the roof of the facility. Then using two cranes the vessels were lifted using a “Top & Tail” technique, which enabled the vessels to be lifted through the roof space in a vertical position and lowered down onto the pallet shoes.  This enabled the vessels to then be skated into the correct position within the facility.

Once the first six vessels were safely positioned the Ainscough team the replaced the section of roof until the second phase commenced.

On completion of the first phase the client commented on how pleased he was with the Ainscough team, especially considering the terrible weather conditions the team were face with over the two days.

We specialise in custom lifting solutions; we have a range of equipment that means we can tailor a solution to your specific needs and taking into account any onsite limitations.

To find out more about our lifting services, contact the Ainscough Industrial Services team today.

Statue Relocation For Manchester Museum

Following on from the relocation of the Rapa Nui (Easter Island) statue to Manchester Museum in 2015, Ainscough Industrial were again called in to assist with the removal of the same statue due to major refurbishment programme which was due to start at the museum.

Relocation-of-Rapa-Nui-Statue-by-Ainscough

On arrival at the museum the Ainscough team first had to move the 3 tonne “Moari Hava” statue and plinth from its original position between two concrete columns.

This was done by using four scoots which enabled the team to move the statue approximately four feet forward into a clear area where a lifting gantry could be erected and the statue could be lifted to remove the plinth and turned through 90 degrees.

Following that the statue was then lowered back onto the scoots ready to be manipulated through the museum doors and onto the outdoor foyer area where it was to be packed and boxed up for the journey back to the British Museum in London to be prepared for display at the Royal Academy in 2018.

The Ainscough team were required to work with diligently and methodically as even with the museum doors and frames removed there was less than 10mm clearance from the top of the statue, and with a conservative value of close to £9m it was vital that the upmost care was taken throughout the project.

Once the statue was carefully packed and boxed up by the British Museum representatives the Ainscough team then used a tele-handler to lift and secure on to the back of a low loader ready for the journey South.

On the completion of the project Manchester Museum’s Sam Beath commented on how pleased she was on how smoothly the project went and also how quickly the Ainscough team managed to complete the job enabling the museum to open as normal without any disruption.

To find out more about specialist relocation service contact the AIS team today.

Ainscough Industrial Successfully Completes Large Press Relocation

Ainscough Industrial were contracted to assist with the relocation of a large hydraulic press from its current location in the facility to a new location on the same site for one of our major blue chip clients.

Large-press-lift-by-Ainscough-Industrial

The first phase of the project involved the match making, disconnection and dismantling of the press which took approximately two weeks.

Once the press had been dis-assembled all the sections and ancillary items were loaded onto transport, provided by Ainscough industrial, and conveyed to the new location within the same site.

Due to the size, position and restrictions of the press the Ainscough team used our Megalift JS400 jacking system along with a 40/60 Versa Lift, 11T Valla Crane and Fork Lift Trucks to ensure all sections were moved safely and securely.

As the press sections were off loaded in the new area the OEM engineers carried out hydraulic upgrade works on each of the sections.

Once these works were completed the Ainscough Industrial team then started work the second phase of re-assembly and re-connection of the hydraulic press onto its new foundations to the complete satisfaction of the client.

For more information on this project, or to get a quote for your own machine lift and relocation, contact our team today.

Client Testimonials

Take a look at some of the great feedback we have received from some of our clients…